Turnout Replacement – Subway Tøyen
Client:
Sporveien AS
Main tasks:
- Replacement of 1x right turnout 1:9
- New contact rails (third rail)
About:
In November 2020, a number of maintenance measures were carried out, including a break of 36 hours, of these 36 hours we were allocated 28 hours for our work. At this time we removed 2 turnouts, where one was rebuilt with changed geometry, new geometry had to be adapted in the breach. The second turnout was replaced with a straight track. Contact rails were also rebuilt.
Construction Time:
February 2021