Sleepereplacement – Rørosbanen 2022

Client:

Bane NOR SF

Main tasks:

  • Aprox 4000 concrete sleepers were changed
  • Full sleeperchange in turnout 32 Elverum
  • Mass replacement Atna station
  • Tamping and trackadjustment
  • Thermitwelding and neutralization

About:

A sleeper exchange of approximately 4,000 sleepers distributed over 3 parcels. Sleeperchanges were carried out both in breaks, but also at white times between trains.

Construction Time:

April – September 2022